posted by R143 on Tue May 18 14:35:16 2004.

The Bleecker and Wall Street rehabs are scheduled to begin in Fiscal Year 2005 (along with quite a few others). The Wall St project could very well complete within the course of the year. The Bleecker St project is very complex, and might take more than a year.